The Delta State Government has issued a strong warning to the contractor responsible for the Orere River Bridge project and the rehabilitation of the Edjekota–Ewu–Orere Road, citing an unsatisfactory pace of work on both sites. The government indicated that it may recommend sanctions if the contractor fails to improve performance.

Commissioner Raises Concerns During Site Inspection

The Commissioner for Works (Highways and Urban Roads), Reuben Izeze, delivered the warning on Friday during an inspection of the projects in Ughelli South Local Government Area. The commissioner expressed displeasure with the level of activity at the sites, accusing the contractor of failing to demonstrate sufficient commitment despite the support it has received from the state government.

According to Izeze, the contractor can no longer use the rainy season as an excuse for the delay. He stressed that the government would not tolerate a situation in which workers appeared at the sites only when ministry officials came for inspection.

“As far as I am concerned, the contractor is not on site, and I must express my strong displeasure with the attitude of the contractor and its pace of work,” the commissioner said.

“While the rain was falling heavily, it was given as an excuse. But today, the rain can no longer be an excuse because I am not satisfied with what I am seeing. It seems this contractor is taking advantage of its relationship with the state government, and that is unacceptable to us,” he added.

Support for Indigenous Contractors Comes With Expectations

Izeze explained that the administration had supported the contractor as part of its efforts to encourage indigenous construction companies to participate in infrastructure development. He, however, cautioned that such support should not be taken for granted, emphasizing that contractors must deliver quality projects within agreed timelines.

The commissioner also accused the contractor of engaging in what he described as window dressing whenever officials visited the sites.

“We have come here after the rain to see this kind of window dressing to make it appear as though they have been busy. For me, it is unacceptable. We have gone beyond the stage of window dressing and trying to be on site only whenever the contractor hears that ministry officials are coming for inspection,” he said.

Contractor Told to Convey Government’s Displeasure

Izeze directed the contractor’s representative to convey the government’s displeasure to the company’s management, warning that another inspection could lead to a recommendation for appropriate action.

“I want the representative of the contractor to pass this message to their principal that if we come here next time and witness this type of situation, we will have no option but to make the appropriate recommendation to our boss in Asaba,” he added.

The commissioner noted that the projects had exceeded their expected timelines and urged the contractor to increase the pace of work so that residents of Orere and Ewu communities could benefit from the infrastructure.

Project Details and Contract History

The Orere River Bridge project, which includes access roads and a spur in Orere Town, was awarded to the contractor on January 27, 2021, at an initial cost of N9.85bn. The contract sum was later reviewed to N32.45bn.

The same company is also handling the rehabilitation and asphalt overlay of the Edjekota–Ewu–Orere Road, awarded on September 3, 2026, at a cost of N6.92bn. The road project was mobilised on September 10, 2026, with a scheduled completion date of March 10, 2028.

The inspection underscores the state government’s determination to hold contractors accountable for project delivery, particularly where public funds and community expectations are at stake. Residents of the affected communities will be watching closely to see whether the warning translates into faster progress on both the bridge and the road.