Share This Post via WhatsApp

Three Transmission Towers Collapse in Nasarawa, Disrupting Power Supply to Keffi and Akwanga

The Transmission Company of Nigeria (TCN) has confirmed the collapse of three transmission towers along the Karu-Keffi-Akwanga 132kV transmission line corridor in Nasarawa State, an incident that has disrupted bulk electricity supply to parts of Keffi and Akwanga.

In a statement issued on Thursday, the company disclosed that the towers, identified as T78, T79 and T80, came down during rainy and windy conditions on Wednesday. The collapse forced TCN to isolate the affected transmission line as a safety measure, leaving all 33kV outgoing feeders at the 132/33kV Keffi and 132/33kV Akwanga transmission substations unavailable.

How the Incident Unfolded

According to TCN, the incident occurred at approximately 4:06pm on Wednesday when the 132kV Karu-Keffi-Akwanga Single Circuit Transmission Line tripped on overcurrent relay protection. The company explained that the trip was triggered during the adverse weather conditions, prompting an immediate investigation into the cause of the fault.

“The Transmission Company of Nigeria hereby informs the public that all 33kV outgoing feeders at the 132/33kV Keffi and 132/33kV Akwanga Transmission Substations are currently unavailable following the collapse of Towers T78, T79 and T80 along the Karu-Keffi-Akwanga 132kV Transmission Line corridor,” the statement read.

Investigations conducted after the line tripped revealed that three transmission towers had collapsed along the corridor. TCN said it promptly isolated the line for safety reasons once the extent of the damage became apparent.

Implications for Electricity Distribution

The development means that electricity distribution companies cannot nominate load on the affected feeders until the damaged transmission infrastructure is repaired and bulk power supply is restored. Transmission substations receive electricity from the national grid and transfer it to distribution companies through lower-voltage feeders for delivery to homes, businesses and other customers. Consequently, damage to a major transmission line can affect several communities even when generation capacity is available elsewhere on the grid.

The incident underscores the vulnerability of electricity supply infrastructure to severe weather conditions, particularly where transmission lines and towers serve as critical links between generating power and distribution networks.

Restoration Efforts Underway

TCN stated that its engineers had already been deployed to the affected location to determine the extent of the damage and the materials and other requirements needed to begin restoration work.

“TCN engineers are currently on site to assess the extent of the damage to enable them to determine the requirements needed to commence restoration activities,” the company said.

The company, however, did not provide a timeline for the restoration of the affected feeders, stressing that the duration would depend on the outcome of the technical assessment and the repair requirements.

TCN Apologises to Affected Customers

TCN apologised to customers affected by the incident and said it was working to restore normal supply as quickly as possible.

“The Company regrets the inconvenience this development will cause electricity customers taking supply from substations affected by the tower incident,” it said. “Please bear with us as we make every effort to ensure that necessary repairs are completed as quickly as possible to enable the restoration of bulk power supply.”

The company added that it would provide further updates as restoration efforts progressed.

Why This Matters

The collapse of the three towers highlights the broader challenges facing Nigeria’s electricity transmission network, where ageing infrastructure and extreme weather events can combine to disrupt supply to entire communities. While generation capacity may remain available on the national grid, the inability to transmit that power through damaged lines leaves distribution companies unable to serve their customers.

For residents and businesses in Keffi and Akwanga, the incident means an indefinite wait for the restoration of bulk power supply, with the timeline hinging on the findings of TCN’s on-site assessment and the logistics of procuring and installing replacement materials. The company’s commitment to providing updates suggests that more information on the repair schedule will emerge as engineers complete their evaluation of the damage.

Rate This Post / Article